Red Seal Refrigeration & AC Mechanic (313A) Official Timed Mock Exam Simulator
Prepare for your Certificate of Qualification (C of Q) exam with our authentic 125-question 4-hour simulation. Built precisely to the National Occupational Standard blueprint with 70% pass threshold verification.
📝 125 Exam Questions
⏱️ 4 Hours (240 Mins)
🎯 70.0% Pass Standard
📊 MWA Diagnostic Scorecard
Ready to Test Your Exam Readiness?
Get full access to the complete 125-question timed exam simulator with instant Journeyperson explanations on every question.
Quick Check
1-Mock Exam Ticket
$14.99 CAD
1 full-length 4-hour timed attempt with detailed MWA diagnostic report.
⭐ Most Popular (Save 33%)
3-Mock Exam Pack
$29.99 CAD
3 full mock exams with uniquely shuffled question sets to track week-over-week progress.
2026 RSOS Blueprint Distribution for Refrigeration & AC Mechanic (313A)
Major Work Activity (MWA)
Target Questions
Exam Weight
MWA A: Occupational Skills & Safety (안전·냉매회수)
13 Qs
10%
MWA B: Piping & Tubing (동관가공·브레이징·기밀시험)
15 Qs
12%
MWA C: Refrigeration Systems (냉매사이클·압축기·팽창밸브)
38 Qs
30%
MWA D: Air Conditioning & Heat Pumps (히트펌프·공조)
34 Qs
27%
MWA E: Controls & Electrical Safety (제어회로·CSA B52)
25 Qs
20%
Total Red Seal Exam Length
125 Questions
100%
Sample Diagnostic Practice Questions
Try these sample questions from our Refrigeration & AC Mechanic (313A) question bank. Select an answer to see instant feedback and explanation.
Q1. A refrigeration mechanic has de-energized a circuit controlling a compressor and applied their personal lockout device. What is the critical next step *before* beginning work, according to standard lockout/tagout (LOTO) procedures?
Worked Explanation: According to standard lockout/tagout procedures, verifying zero electrical potential using a calibrated voltage tester is a mandatory step after de-energizing and locking out equipment, and before commencing work. This ensures the equipment is truly de-energized and cannot be re-energized inadvertently. Attempting to start the equipment (B) is part of verifying isolation but is not the primary method for confirming zero electrical potential at the work point. Informing personnel (A) is good practice but not the critical next safety step for the individual. Tagging (D) is part of the LOTO process but not the verification of zero energy.
Q2. A refrigeration mechanic is installing new copper piping for a high-pressure R-410A system. The pipe joints are to be brazed. According to CSA B52, what minimum percentage of silver content is required in the filler material for brazing joints in refrigerant piping?
Worked Explanation: CSA B52 (e.g., Clause 11.2.3.2) specifies that brazing alloys used for refrigerant piping shall have a melting point above 540°C (1000°F). It does not explicitly require a minimum silver content, as phosphorus-copper (Phos-Copper) alloys, such as BCuP-2 or BCuP-5, which contain no silver or minimal silver, are commonly used and meet strength requirements for R-410A applications. The key is the melting point and strength for the required operating pressures, not necessarily silver content. Therefore, 0% silver content is permissible if the alloy meets other strength and melting point criteria.
Q3. A refrigeration mechanic is commissioning a new R-404A medium-temperature supermarket display case system. The design specifications call for a 10°F (5.6°C) superheat at the evaporator outlet and 8°F (4.4°C) subcooling at the liquid line sight glass. After startup and stabilization, the following readings are recorded:
- Evaporator suction pressure: 30 PSIG (R-404A saturation temp: 0°F / -17.8°C)
- Suction line temperature at evaporator outlet: 12°F (-11.1°C)
- Condenser discharge pressure: 250 PSIG (R-404A saturation temp: 95°F / 35°C)
- Liquid line temperature at condenser outlet: 85°F (29.4°C)
What superheat and subcooling values should the mechanic document, and what is the most likely immediate implication for the system's performance relative to design?
Worked Explanation: First, calculate the superheat and subcooling from the given readings:
Superheat (SH) = Suction Line Temperature - Evaporator Saturation Temperature
SH = 12°F - 0°F = 12°F
Subcooling (SC) = Condenser Saturation Temperature - Liquid Line Temperature
SC = 95°F - 85°F = 10°F
Comparing these to the design specifications:
Design SH: 10°F, Actual SH: 12°F (Actual is 2°F higher than design)
Design SC: 8°F, Actual SC: 10°F (Actual is 2°F higher than design)
Both the superheat and subcooling are higher than their respective design targets. High superheat typically indicates a starved evaporator (undercharge, restricted metering device, low load). High subcooling typically indicates an overcharge or a restriction in the liquid line/condenser outlet. When both superheat and subcooling are elevated, a common cause is a liquid line restriction (e.g., a partially plugged filter drier, kinked line, or partially closed king valve) or a system operating under very light load with an incorrect charge. An overcharged system would usually have low superheat, and an undercharged system would typically have low subcooling. Therefore, option A provides the most plausible diagnostic implication for both values being above design.